One of the questions I’ve been asked quite a few times over the years is what a producer needs to put in place when they first start with a team. Quite often it’s a question about documents. What do I need to produce? Do I need a risk register? What should I have on my board?
I’d rather start by looking at what the team needs. You could spend your first two weeks producing some rather lovely documents and at the end of it still not know who can make a decision about the game or why somebody has been waiting a week for a piece of work from another team.
I’ve recorded another episode in which I look at the smallest production system I’d be comfortable starting with. There are four things I’d want to understand and, where necessary, help the team put in place: direction and responsibility, shared working agreements, visible information and an operating rhythm.
What have you been asked to produce?
Imagine you’ve joined a team that’s at the beginning of making a game. There’s quite a lot that you don’t know yet, and some of what you’re going to be doing over the next few weeks is working out whether the ideas people have for the game are going to work. What do you need to prove next? As a producer, you’ll want to give people the opportunity to experiment, but you’ll also need to know how much time and effort the team can afford to spend on those experiments.
Now imagine you’ve joined a team that’s halfway through making a game. There are commitments you haven’t been involved in making. What has already been agreed, what’s integrated into the game and what’s expected at the next milestone?
Similarly, you might be working at an external development studio producing art for someone else’s game. You’re going to want to know what the client is expecting, what has actually been accepted and how the two companies work together. If you’re working on a live game, there are people playing it whilst you’re developing new features and content. How are you going to make changes without damaging the experience they’re having now, and how will you respond if something goes wrong?
We need to understand the nature of the work before deciding how to organise it. Discovery, delivery through an established pipeline and providing an ongoing service can all happen within the same game team. I don’t see why we’d necessarily want to organise all of that work in exactly the same way.
1. Direction and responsibility
The first thing I’d want to know is what we’re working towards. What’s the next meaningful outcome for the team, what are we expected to deliver and how will we know whether we’ve done it?
Then I’d want to understand who owns the decisions that affect that work. I might be able to agree with the team which piece of work we’re going to do next, but that doesn’t necessarily mean I can decide to remove something from the scope of the game. Who owns that decision? Who decides whether an asset meets the technical standards or whether an external deliverable has been accepted?
There are some particularly useful things you might discover by asking those questions. Perhaps all the work coming in from an external art team needs to be approved by one person. That person may also have quite a lot of other work to do. You now know something about the way the work is going to flow, and you can have a conversation with the relevant people about how you’re going to manage it.
As a producer, you don’t have to own every decision. You do need to know who does, and you can take responsibility for helping those decisions happen.
2. Shared working agreements
Let’s say we’re making an asset for a game. We’ve got some concept art, someone’s going to model it, the art needs to be approved, it needs to be technically validated and, in this example, it’s going to be handed over to a client for acceptance.
Somebody tells you the asset is done. What exactly have they told you?
It could be that the model has been finished, but nobody has approved it yet. Perhaps the art has been approved but the technical artist is still waiting for something. Perhaps it’s passed all of those stages but the client hasn’t accepted it.
It’s particularly important that the people who are handing work over to one another have a shared understanding of what words like ready, done, accepted and blocked mean. You don’t necessarily need to write pages of definitions, but you do want people to be able to plan their work based on what someone else tells them.
There’s also a question of how we want people to behave when they’re uncertain about something. If somebody tells you they’re confident about a piece of work being ready next Friday, what information have they used to come to that judgement? If they know there’s a problem, do they feel comfortable telling you about it?
If we want people to raise concerns early, we have to do something with the information they give us. Even if we decide not to change anything, it would be rather useful for the person who raised the concern to understand why.
3. Visible information
There are five kinds of information I’d want to be able to see. I haven’t called these five documents because some of this information may already be available in the software the team uses to manage its work.
- A near-term plan: What are we trying to achieve next, by when and what will we use as evidence?
- Risks, assumptions, issues and dependencies (RAID): What are we uncertain about, what have we assumed, what has already gone wrong and what are we relying upon? A small team might only need a light view of its principal risks and issues, with assumptions and dependencies recorded where they matter.
- Dependencies and blockers: Who needs what from whom, by when, and what has actually been agreed? What is stopping work now? This can be a view of information already held elsewhere rather than another register.
- Decision records: What was decided, why, by whom and when? Who needs to know about it?
- A work board: What’s being worked on, what’s waiting, what’s blocked and what has been completed? How does the work relate to the outcome we’re trying to achieve?
There’s something I particularly like about putting a risk register together when you first join a team. People are probably going to spend quite a lot of time telling you about things they’re worried about. Some of those concerns may have been there for months.
When you record those things, agree who’s going to look into them and come back to the people who raised them, you’re demonstrating that you’ve listened to them. The register on its own doesn’t do that. It’s what you do with it that matters.
Similarly, I’ve seen people make quite significant decisions and forget to communicate them to the people whose work is going to be affected. They may even have recorded the decision somewhere. We’ll come back to that in a moment.
Every piece of information we decide to maintain needs a purpose, someone responsible for keeping it current, a point at which we review it and somewhere people know they can find the reliable version.
4. Keeping the system alive
This is the bit I’d spend quite a lot of time on with a new producer. You’ve got your direction and responsibilities, you’ve agreed how you’re going to work and you’ve got the information you need. What are you going to do with it?
I talk about cadence a great deal in my studio risk management teaching, because there’s not much value in having a risk register if the information goes into it and nothing comes out of it. The same applies to the other parts of the production system.
There are a few things I’d want us to be doing regularly. We need to coordinate the work, so people aren’t left waiting for things we could help them get. We need to review our plans, risks and dependencies, and work out what needs changing. We also need to look at what we’ve actually produced. If we’re heading towards a milestone, are we producing the evidence we’re going to need to make a decision at that milestone?
Then there’s the question of how we improve the way we work. I covered this in my episode about finding time for continuous improvement. Is there one thing we could try doing differently which might make next week a little better than this week?
Read the accompanying article: How do we improve production when we’re already too busy?
I’m not suggesting you need to organise four more meetings. You might already have a regular meeting in which the team reviews its work. Can we use some of that time to talk about a dependency that’s becoming a problem? If we’re already looking at a build every Friday, can we use what we learn from that to make some decisions about the plan?
Agree who needs to be involved in these conversations, who takes responsibility for the actions and when you’ll come back to them. Don’t wait for a scheduled review if you need a decision now. If a concern needs to be escalated, know who to go to and act when required.
How would all of this work on Beaconbound?
Let’s go back to Beaconbound, the fictional four-player co-operative exploration game I’m using throughout these episodes. Imagine we’ve got a twenty-person team in early pre-production. We’re working on the first landing site and a signal relay. In six weeks we want to be able to play from landing through to repairing the relay on our target PC.
We have an outcome to work towards, and we know the game director owns the decisions about product direction. We’ve got some questions to resolve about what we mean by integrated and playable, and about how the various disciplines are going to hand work over to one another.
Our near-term plan, work board and other information need to help us get to that demo. Let’s say we’re relying on the engineering team to resolve a problem before other work can be integrated. We want to understand what is being asked of them, when we need it and what will happen if they can’t do it. If there’s a decision we need to make before the halfway point, we don’t want to discover that on the day of the demo.
For this example, let’s agree to have a short daily conversation about anything that’s blocking work, a Friday production review in which we also look for one improvement, a build check at week three and a demo and decision at week six. We’ve now got a way of bringing the four elements together.
Follow one decision through the system
One of the questions we need to resolve is whether operating the relay should require two players. We could make it something one player does, or we could require all four. Let’s get the people who understand the work to look at the options and the implications for design, engineering and QA. In this fictional example, the game director decides that two players should operate it together within the four-player session.
We’ll record what’s been decided, who decided it, why and when. And then we’ll communicate it to the people whose work it affects.
There’s something quite interesting about that conversation. We might go to one of those people and discover something about the implications of the decision that we hadn’t considered. We can take that information back to the game director, who may or may not want to change the decision. Either way, we’ve learnt something rather useful that we wouldn’t have learnt by simply putting the decision in a log.
Now we need to make sure the work and the acceptance criteria reflect the decision, understand any changes to our dependencies and follow through at the week-three build check. If the evidence isn’t what we expected, we can have another conversation about what to do. We haven’t assumed that the decision has worked just because it has been made.
Your first two weeks
If you were joining a team on Monday, I’d suggest spending some time finding out how the team actually works before you try to change anything. What’s the team trying to achieve? Where do decisions get made? How does work move from one person to another? What information are people having difficulty finding or relying upon? What meetings are already in place?
You might discover something relatively small you can help with. Perhaps an important decision needs communicating, or there are two people in different disciplines who’ve been trying to resolve a handover problem. If you can help the team make one useful improvement, people have already got a reason to trust you when you come to talk to them about something else.
There’s a related question worth coming back to after a few weeks. Are people raising concerns earlier? Are we resolving dependencies? Do the people affected by decisions actually know about them? Are actions being followed through? Can the team point to something that’s improved because of the way we’ve organised ourselves?
Those are the sorts of things I’d be looking for. I wouldn’t be particularly interested in counting the number of documents we’ve produced or meetings we’ve put in place.
Start with the team, not with the system you think you’d like to impose on them.
I’ve put together a free Game Producer’s Starter Kit which includes a production system canvas, a health check, some practical templates and a worked example from Beaconbound. You can get the Starter Kit here. I’d start with the canvas and health check rather than trying to use everything in the pack.